To view or download information from the June 2010 Public Information Session, including the Project Schedule, please click here

North-South Corridor Area:

17 Avenue SE:

Traffic Pattern Changes:

  • Approved 24-hour dirt work near the 17 Avenue area is scheduled to be completed the week of February 20, 2012 . Please note that some noise disturbances may occur. We apologize for this inconvenience.
  • Traffic was switched onto a temporary detour in November 2011.  Two-way traffic on 17 Avenue SE will be maintained at all times.
  • Topsoil, vegetation clearing, earthworks and road preparation work underway on the south side of 17 Avenue SE.
  • Earthworks and paving north of 17 Avenue SE are now underway.  
  • Piling work to continue through Winter 2012.
  • Substructure work to begin in Summer 2012, with superstructure construction, including girder installations, scheduled for Summer 2012.

Peigan Trail SE:

Traffic Pattern Changes:

  • No new traffic pattern changes at this time.
  • Grading and substructure concrete work largely completed.
  • Earthworks underway and to continue in Spring 2012 to build the interchange.
  • MSE wall installation at CN Crossing underway.
  • No structural work anticipated in this area until Winter/Spring 2012. 
  • Girder installation and bridge deck construction to begin in Summer 2012.
  • 50 Avenue is permanently closed between 68 Street SE and 84 Street SE for road realignment work. 

61 Avenue SE:

Traffic Pattern Changes:

  • No traffic pattern changes at this time.
  • Earthworks preparation has been completed at 61 Ave SE north of Glenmore Trail SE, south of 50 Avenue SE.
  • Grading and paving in this area to continue throughout 2012.
  • Utility work, foundation and bridge structure work has begun.
  • MSE walls, girder installation and bridge deck construction to begin in mid-2012.


Glenmore Trail SE:

Traffic Pattern Changes:

  • Traffic was shifted onto a temporary detour on Glenmore Trail and 84 Street SE. Two-way traffic on Glenmore Trail and 84 Street SE will be maintained at all times. Motorists are anticipated to use this detour until the Fall of 2012.
  • Roadwork, utilities and earthworks ongoing, with topsoil stripping underway north and south of Glenmore Trail SE and north of 106 Ave SE within TUC.
  • Piling works have been largely completed.
  • Substructure work to commence in Spring 2012, with structure works continuing in mid-2012.
  • Structural work over the W.H. Canal is also underway through 2012.

114 Avenue SE:

Traffic Pattern Changes:

  • No traffic pattern changes at this time.
  • Topsoil stripping and earthworks to continue throughout Spring 2012.  
  • Utilities construction anticipated to be completed in Spring 2012.
  • Substructure and superstructure work, including girder installations, to begin in Spring 2012.



130 Avenue SE:

  • No significant construction activity anticipated until August 2012.
  • This is grading work is for a future interchange to be built at this location. The timing for this interchange is not yet known and will be dependant upon future development activity adjacent to SE Stoney Trail.