North-South Corridor Area:
17 Avenue SE:
Traffic Pattern Changes:
- Approved 24-hour dirt work near the 17 Avenue area is scheduled to be completed the week of February 20, 2012 . Please note that some noise disturbances may occur. We apologize for this inconvenience.
- Traffic was switched onto a temporary detour in November 2011. Two-way traffic on 17 Avenue SE will be maintained at all times.
- Topsoil, vegetation clearing, earthworks and road preparation work underway on the south side of 17 Avenue SE.
- Earthworks and paving north of 17 Avenue SE are now underway.
- Piling work to continue through Winter 2012.
- Substructure work to begin in Summer 2012, with superstructure construction, including girder installations, scheduled for Summer 2012.
Peigan Trail SE:
Traffic Pattern Changes:
- No new traffic pattern changes at this time.
- Grading and substructure concrete work largely completed.
- Earthworks underway and to continue in Spring 2012 to build the interchange.
- MSE wall installation at CN Crossing underway.
- No structural work anticipated in this area until Winter/Spring 2012.
- Girder installation and bridge deck construction to begin in Summer 2012.
- 50 Avenue is permanently closed between 68 Street SE and 84 Street SE for road realignment work.
61 Avenue SE:
Traffic Pattern Changes:
- No traffic pattern changes at this time.
- Earthworks preparation has been completed at 61 Ave SE north of Glenmore Trail SE, south of 50 Avenue SE.
- Grading and paving in this area to continue throughout 2012.
- Utility work, foundation and bridge structure work has begun.
- MSE walls, girder installation and bridge deck construction to begin in mid-2012.
Glenmore Trail SE:
Traffic Pattern Changes:
- Traffic was shifted onto a temporary detour on Glenmore Trail and 84 Street SE. Two-way traffic on Glenmore Trail and 84 Street SE will be maintained at all times. Motorists are anticipated to use this detour until the Fall of 2012.
- Roadwork, utilities and earthworks ongoing, with topsoil stripping underway north and south of Glenmore Trail SE and north of 106 Ave SE within TUC.
- Piling works have been largely completed.
- Substructure work to commence in Spring 2012, with structure works continuing in mid-2012.
- Structural work over the W.H. Canal is also underway through 2012.
114 Avenue SE:
Traffic Pattern Changes:
- No traffic pattern changes at this time.
- Topsoil stripping and earthworks to continue throughout Spring 2012.
- Utilities construction anticipated to be completed in Spring 2012.
- Substructure and superstructure work, including girder installations, to begin in Spring 2012.
130 Avenue SE:
- No significant construction activity anticipated until August 2012.
- This is grading work is for a future interchange to be built at this location. The timing for this interchange is not yet known and will be dependant upon future development activity adjacent to SE Stoney Trail.